Downtown Orlando Development: The Arena District and the Housing Market

A $500 million plan next to Kia Center, a 10-acre public space approved under I-4, finished and unfinished street work, and a close look at nearby housing.

By Jared JonesNovember 23, 202616 min readOrlando GrowthLast updated: November 2026Winter Garden & Horizon West Real Estate Hub
Aerial view of downtown Orlando high-rise apartment and office towers with a church steeple and city streets below

Downtown Orlando’s high-rise core, where the next wave of projects is filling in around the west side and the arena.

Downtown Orlando development at a glance

1

Westcourt is the headline, not a finished building. The city’s snapshot still lists the $500 million, 8.43-acre plan beside Kia Center as proposed. Early site work has been reported, but an official groundbreaking is the milestone to watch.

2

Creative Village is the part of the map that is actually moving. The Beacon’s 115 apartments are open, and Parcel H is under construction with a 2027 target, on the former arena site west of downtown.

3

Nearby housing is not one story. In Jared’s review of the last 12 months of MLS data, College Park sale prices were up about 6%, the rest of 32804 was softer, and typical downtown condo prices were down versus a year earlier.

Downtown Orlando development right now is less about another condo tower and more about a west-side district next to Kia Center, a planned public space under I-4, and street work already underway. The $500 million Westcourt plan is the flagship, while nearby housing in 32804 and downtown condos are telling a more mixed story.

Jared walks through downtown Orlando’s next wave of projects, then the housing numbers in 32804, College Park and downtown condos. The video premiered November 22, 2026.

This post is the longer companion to our short answer page on what the $500 million Arena District, officially called Westcourt, actually is. Use that page for the Westcourt program in one place. What follows is the wider status map, plus the nearby housing figures Jared reviewed in the video.

What is the flagship project in downtown Orlando development right now?

The flagship is Westcourt, a $500 million mixed-use plan on 8.43 acres beside Kia Center at Church Street and Hughey Avenue. That is the official name on the city’s Downtown Development Board snapshot. Marketing and the video title often say Arena District because the site sits directly next to the arena, on the west side of downtown in ZIP code 32801.

The city’s page lists 273 apartments, a 260-room hotel, 125,000 square feet of retail, about 200,000 square feet of office, 80,000 square feet of event space and 2,300 integrated parking spaces. It still describes the project as proposed, and it does not post a start date or a completion date. When sources disagree on unit or hotel counts, start with the city snapshot and treat later news figures as reporting, not a substitute for the official page. The short Westcourt answer page walks through those differences in more detail.

Jared describes a roughly 900,000 square foot district just north of Kia Center, with a Kimpton hotel, residences, Class A office, retail and dining, and a live entertainment venue. Those size and direction details appear in May 2026 news coverage as well. They are not on the city’s snapshot, which only says the site is adjacent to the arena. He also notes that Turner Construction was signed in the spring and that early site work, including surveying, utility mapping and test piles, has started. That is real work, he says, but it is not a groundbreaking.

Watch the dates. Jared says that when Westcourt was approved, it was supposed to open in 2027, and that the target is now late 2028. He treats even that later date as a target, not a guarantee. February 2026 reporting had already pointed to financing delays and a 2028 opening as a discussed goal. The milestone he is watching is an official groundbreaking. For earlier context on how the plan was first framed, see our earlier Westcourt district update.

Concept graphic of the planned Westcourt district north of the Kia Center showing a Kimpton hotel, residences, Class A office space and retail and dining

How the planned Westcourt district lays out next to the arena. Conceptual massing, not final architecture.

Graphic: conceptual massing based on Westcourt renderings. Some visuals AI-generated for illustration.

Downtown Orlando projects: where each one stands

  • Westcourt (Arena District): Proposed on the city page; early site work reported. $500 million and 8.43 acres (city); about 900,000 square feet north of Kia Center (news and video) (As of November 2026)
  • Creative Village: Phase 1 complete; Phase 2 under construction. 68 acres; $2 billion full buildout (As of November 2026)
  • Parcel H: Under construction. About $60 million; 7 stories; completion targeted for 2027 (As of November 2026)
  • The Beacon at Creative Village: Open and leasing. 115 apartments with income limits; $40 million (Opened October 2026)
  • The Canopy under I-4: Approved; a clear construction start not yet announced. About 10 acres; $30 million (city) (As of November 2026)
  • Magnolia Avenue two-way conversion: Finished. South Street to Livingston Street; $2.8 million (Reopened September 2026)
  • Church Street festival street: Phase I under construction; later phases not yet built. Garland Avenue to Magnolia Avenue; later phases targeted into 2028 (As of November 2026)
  • Camping World Stadium renovation: Under construction. $400 million; targeted for summer 2027 (As of November 2026)

What is actually being built at Creative Village?

Creative Village is the innovation district on the former arena site, and it is the part of downtown where buildings are actually going up. The city’s Downtown Development Board profile describes 68 acres and a $2 billion full buildout, anchored by the UCF and Valencia downtown campuses, offices, apartments and Luminary Green Park. Phase 1 was completed in August 2022. Phase 2 is underway.

Just north of Westcourt, this is the stop Jared points to if you would rather see a finished building than a rendering. Parcel H is a 7-story mixed-use building south of Luminary Green Park. Creative Village materials describe a roughly $60 million project, with apartments over ground-floor commercial space and construction that began in January 2026, targeted for completion in 2027. Public summaries of the apartment count have not lined up exactly, so this post does not lock in a single unit number.

The Beacon is further along. It is a 5-story building with 115 apartments reserved for households at or below 80% of area median income, with that affordability required for 50 years. City and news accounts from October 2026 marked a grand opening, with 62 of the 115 units leased at opening and an investment of about $40 million. It is part of the city’s Orlando Unlocked effort, and it sits in the Creative Village and Parramore area, not in the high-rise core around Orange Avenue.

Creative Village is not finished, but it is moving. If you are comparing this west side of downtown with other large plans nearby, our look at the Parramore Green District plan is useful context for the same edge of downtown. A wider status check on Orlando’s big projects heading into 2027 helps separate what is open, what is under construction and what is still on paper.

Aerial view of Creative Village in downtown Orlando with apartment towers, campus buildings and a green park

Creative Village from above, with campus buildings, apartments and green space already on the ground.

Map of Creative Village in downtown Orlando showing apartments, offices, Luminary Green Park, Parcel H and the UCF and Valencia downtown campus

Creative Village, the innovation district on the west side of downtown, with Parcel H near Luminary Green Park.

Map data: OpenStreetMap contributors. Boundaries and footprints approximate.

What is The Canopy, and when does the space under I-4 change?

The Canopy is the city’s plan to turn about 10 acres under I-4 into public space, funded with $30 million in city redevelopment money, and it is approved but not clearly under construction yet. The official city page compares the idea to a ground-level version of a signature urban park, with an anticipated start in the third quarter of 2026 and completion in the fourth quarter of 2027, over about 18 months.

Jared places the corridor from south of Church Street to north of Washington Street, between Garland Avenue and Hughey Avenue. News coverage from August 2026 describes the same general boundaries and a mix of event space, lighting, paths, landscaping, parking and a rideshare area, including nearly 300 parking spaces. This is not meant to be only a park. The city’s goal is to stitch the west side of downtown back together under the interstate.

City Council gave final approval in August 2026. The city’s own start window was the third quarter of 2026. Jared says a later start window closed on October 9, and that as of his recording he had not seen a start announced. He would only call it under construction once equipment is on site. That is the right way to read it as of mid-November: approved, funded and still waiting on a clear start, after dates have already slipped.

If a photo of the construction fence shows banners that mention 2027, treat that as on-site messaging consistent with the city’s completion target, not as a posted construction schedule. For other downtown connectivity plans already covered on this site, see the O-Line trail and future development overview.

Construction fence under the I-4 overpass in downtown Orlando with banners reading Canopy coming 2027

The space under I-4 today, fenced off with banners for The Canopy. Treat on-site signage as messaging, not a posted start date.

Which downtown street projects are finished, and which are still ahead?

Magnolia Avenue is the one street project on this map that is already finished, while Church Street’s festival-street rebuild is underway in phases that run into 2028. The city converted Magnolia from one-way back to two-way traffic between South Street and Livingston Street, removed most of the dedicated LYMMO bus lane and added on-street parking. The job was budgeted at $2.8 million, broke ground on February 10, 2026, and reopened in September 2026. Official materials say Magnolia was made one-way in the 1950s, after I-4 was built. Jared says 1956; the official sources we checked do not pin that exact year, so this post uses the 1950s wording.

Church Street is being rebuilt as a festival street from Garland Avenue east to Magnolia Avenue. The city’s plan is in three phases: Phase I, from Garland to the railroad tracks, in winter 2026; Phase II, from the railroad tracks to Orange Avenue, in spring 2028; and Phase III, from Orange Avenue to Magnolia Avenue, in early summer 2028, including a two-way conversion with integrated LYMMO service. Phase I is a curbless, pedestrian-first redesign, and construction is underway. Jared would hold the later dates loosely, given how other downtown timelines have moved.

He also flags work that is still on the drawing board. Orange Avenue and Rosalind Avenue are next for two-way conversion, he says, and they are still in design. On the College Park side of the map, in 32804, he points to a first piece on Edgewater Drive: a roundabout at Edgewater and Lakeview. In his update, the city expected to award a contractor this winter and start construction next year, with wider sidewalk work depending on later funding. His honest take is that more walkable streets are the goal, but people who commute through these corridors should expect detours for a while.

In the middle of downtown, he also notes a change at Lake Eola. In July, he says, the city moved its last 42 captive swans to a sanctuary after an avian flu outbreak, ahead of a planned park renovation he puts at $60 million. That swan and budget detail comes from his video, not from a fresh official page check in this draft. For the earlier public-space context, see our Lake Eola Park upgrades overview, and for how these close-in streets feel to live on, see Living in Historic Downtown Orlando.

Map of Magnolia Avenue in downtown Orlando between Livingston Street and South Street marked as now running two ways

Magnolia Avenue, the one street project on this map that is already finished.

Map data: OpenStreetMap contributors. Source: City of Orlando.

$500 millionWestcourt investment listed by the City of Orlando
10 acresPublic space planned under I-4 for The Canopy
$215,000Typical downtown condo sale in Jared’s latest 12-month review, versus about $270,000 a year earlier
6%College Park typical sale-price gain in Jared’s review, while the rest of 32804 was softer

What is the downtown Orlando and 32804 housing market doing?

The nearby housing market is split: College Park has been firmer than the rest of 32804, and downtown condos in 32801 have offered more negotiating room. Every housing figure in this section is from Jared’s review of the last 12 months of MLS data, compared with the year prior. These are his observations, not a public government report, and they can move as new sales post.

He starts with 32804, and he treats the ZIP code as two places. The typical home in the whole ZIP sold for $588,000, up less than 1% from the year before, which is basically flat. Split it, and the stories diverge. In College Park, the typical sale went from about $616,000 to $655,000, up 6%. In the rest of 32804, it went from about $444,000 to $425,000, down around 4%. He cautions that the non-College Park side is a smaller pool, with 86 sales, so that 4% should be held loosely. Part of College Park’s gain is mix: nearly one in five sales there was new construction, which pulls the typical price up on its own. The 6% gain is a real number in his data, but it is not proof that downtown development is lifting College Park values.

Across the ZIP, homes were taking longer to sell, with days on market going from 19 to 26, still a relatively short window. Sellers were getting around 98% of asking price, and one out of three homes still sold over asking. Homes under $500,000 went from 40% of 32804 sales to 37%, and in College Park alone that share fell from 35% to 28%. As of his snapshot, 19 College Park homes were under contract with a median list price of $1.1 million. Those are asking prices, not final sale prices. Price per square foot in 32804, he says, has stayed between $343 and $359 every quarter for the last two years. If you are waiting for a crash in 32804, his numbers do not show one. If you are waiting for a boom from projects like Westcourt, the ZIP-wide numbers do not show that either. The better question is which part of 32804 you are actually shopping in.

For more negotiating room, he looks at downtown condo sales in 32801. The typical downtown condo sold for around $215,000, versus about $270,000 a year earlier. Price per square foot was down about 10%, from $282 to $253. Days on market went from 70 to 83, and 46% of those condos sat 90 days or more. Some of the drop is mix: smaller units sold this year, which pulls the typical price down. In the most recent six months of his data, the median was $248,000, versus $211,000 in the earlier six, with price per square foot roughly flat around $253 to $255. His read is that downtown condos are a negotiation, not an automatic bargain. If a unit has been sitting for three months, that matters. Before buying any condo, he would ask about milestone inspections, a reserve study and special assessments, because a lower price can still come with a large bill, and monthly assessments have been rising.

Inventory is thinner, but that has not handed sellers 2021-style pricing power. In 32804, the number of sellers bringing homes to market was down 30% from a year earlier, while countywide inventory was down only 2.6%. About 27.5% of 32804 listings and 27.7% of 32801 listings had cut the price, versus about 30% countywide. Median asking prices in his snapshot were $645,000 in 32804, up 2.2%; $338,000 in 32801, up 0.8%; and $430,000 in Orange County overall, down 0.9%. He also shares average insurance quote estimates of about $5,400 a year in 32804, $5,200 in 32801 and $3,500 countywide. Those are estimates, and anyone buying should get a real quote before relying on them.

Aerial view across Lake Concord toward I-4 and downtown Orlando apartment and office buildings

I-4 and the edge of downtown from Lake Concord, a reminder of how close in-town neighborhoods sit to the core.

What should you watch next in downtown Orlando development?

The four markers Jared is watching are an official Westcourt groundbreaking, dirt moving at The Canopy, a contractor award for the Edgewater work, and whether the downtown condo market keeps stabilizing. Until those show up in official notices or on the ground, treat renderings and target dates as a plan, not a finished result. Timelines on large downtown jobs have slipped before, and he is careful to say that not every promised project comes through on the first schedule.

Two other projects sit just off the core map. If you have driven by Camping World Stadium, the $400 million renovation is underway, paid for with Orange County tourist development tax revenue and targeted for summer 2027. Events are expected to continue during construction. We have already covered a related stadium-area upgrade in our Camping World Stadium garage and site-improvement post, so this update does not relitigate that earlier garage project.

West of College Park, at Princeton Street and Orange Blossom Trail, Jared notes a proposal for 331 apartments and townhomes on the old Princeton Commerce Center site. He is clear that it is proposed and not yet approved. Until the city acts, it belongs on a watch list, not on a list of jobs that are underway.

If you are trying to place all of this in a longer downtown investment story, our earlier look at downtown Orlando investment and what it means for real estate and the broader roundup of major Central Florida projects are useful background. For the west Orange side of the metro, start with the Winter Garden and Horizon West 2026 hub.

Map of The Canopy planned public space under I-4 in downtown Orlando between Washington Street, Garland Avenue, Hughey Avenue and Church Street

The Canopy’s planned footprint under I-4. Approximate area.

Map data: OpenStreetMap contributors. The Canopy shown as a planned, approximate area.

A light real estate read

The nuance a downtown-wide headline can hide is how local these changes really are. A condo in 32801 that has been sitting for three months is a different decision than a College Park house that still drew an over-asking offer, and both are different from a block that will live next to Church Street construction for the next two years. Close-in neighborhoods around downtown are largely built out, so the new supply that does appear tends to be a rebuild, a mid-rise or a project on a site that already had something on it. That is one reason 32804 can look flat until you split College Park from the rest of the ZIP. It is also why a project like Westcourt or The Canopy can change the feel of the west side without automatically rewriting sale prices a mile away. If you want a street-level sense of the older neighborhoods around the core, start with our comparison of historic downtown Orlando areas, then look at the specific building or block you are actually considering, including construction calendars, assessments and how you would get in and out during the next few years of street work.

The Takeaway

Downtown Orlando development is in a messy middle: Westcourt is the $500 million headline still waiting on an official groundbreaking, Creative Village is the place where buildings are already opening, The Canopy is approved under I-4 but not clearly started, and Magnolia Avenue is the rare project that is already done. The housing story next door is just as mixed. In Jared’s review, College Park has been firmer than the rest of 32804, and downtown condos have offered more room to negotiate. Watch the groundbreaking, the Canopy site, the Edgewater contractor award and whether condo prices keep stabilizing, and use official city pages plus current sales, not renderings, before you treat any of this as a sure thing.

FAQ

Is Westcourt the same thing as the Arena District?

Yes, in the way those terms are being used here. Westcourt is the official project name on the city’s Downtown Development Board page. Arena District is the informal name used in marketing and in the video title, because the site sits next to Kia Center at Church Street and Hughey Avenue in downtown Orlando. If you are searching city records or later permit notices, look up Westcourt.

Has construction started on Westcourt or The Canopy?

Not in the sense of an official groundbreaking that closes the question. The city still lists Westcourt as proposed, while news reports and Jared’s video describe early site work such as surveying, utility mapping and test piles. The Canopy is approved and funded at $30 million, with a city completion target in late 2027, but Jared had not seen a construction start announced as of his recording. The clean test is official notices and equipment on site.

What is already finished on the west side of downtown?

Magnolia Avenue is the finished street project, now running two ways between South Street and Livingston Street after a $2.8 million rebuild that reopened in September 2026. At Creative Village, Phase 1 is complete, and The Beacon opened in October 2026 with 115 apartments reserved for households at or below 80% of area median income. Parcel H is under construction, not finished, with a 2027 completion target.

Is the nearby housing market rising because of these projects?

Not in a simple ZIP-wide way. In Jared’s review of the last 12 months of MLS data, the typical 32804 sale was about $588,000, basically flat. College Park was up about 6%, while the rest of the ZIP was down about 4% on a smaller sample. New construction made up nearly one in five College Park sales, which can lift typical prices. Downtown condos in 32801 were down versus a year earlier, though the most recent six months looked firmer.

What should buyers and sellers watch before making a move near downtown?

For the projects, watch an official Westcourt groundbreaking, a clear start at The Canopy and later street-work dates that have already proven willing to move. For housing, look at the specific part of 32804 or 32801 you are shopping, days on market, price per square foot and, for condos, reserve studies, milestone inspections and special assessments. Call or text 407-706-5000 or email info@jaredjones.com if you want help reading a specific property against this map.

Thinking about buying or selling near downtown Orlando?

Get a straight read on which neighborhood, building and price tier fit your plans. Call or text 407-706-5000 or email info@jaredjones.com.

Author

Jared Jones

Written by Jared Jones, Broker Associate with the Jared Jones Team, Brokered by eXp Realty, serving Winter Garden and the greater Orlando and Central Florida area. 24 years in real estate and nearly 4,000 homes sold. Project details come from City of Orlando, Downtown Development Board and developer sources, checked in November 2026. Housing figures are Jared’s own review of the last 12 months of MLS data, compared with the year prior. The companion YouTube video premiered November 22, 2026. We help buyers and sellers in accordance with Fair Housing laws.