When Will Wellness Way Connect to Horizon West? (2026)

Quick answer
As of November 2026, there is no open connection yet. Orange County is extending New Independence Parkway about one mile to the Lake County line, where it meets Wellness Way. Construction runs from September 2025 through early 2027, so the connection is expected to open in early 2027.
| Fact | Figure |
|---|---|
| New Independence Parkway extension length | About 1 mile |
| Roadway type | Four-lane divided |
| Lanes each direction | Two 11-ft lanes |
| Multi-use path | 10-ft path each side |
| Construction window | September 2025 to early 2027 |
| Project cost | $14.5 million |
| Progress as of March 31, 2026 | More than 54% |
Sources: Orange County Government New Independence Parkway project page and Orange County Public Works Newsletter #1 for length, roadway type, lanes and construction window; The Orlando Real for project cost and progress; Spectrum News 13 for the daily traffic figure (all checked November 18, 2026).
In this July 2, 2026 video, Jared Jones drives the Winter Garden area and points west toward Clermont to explain how a new road will tie Horizon West to Lake County. He walks through the Wellness Way and New Independence Parkway connection and what he thinks it will do to traffic and growth. This page checks the official timeline and separates the verified facts from his on-camera estimates.
When will the Wellness Way connection to Horizon West open?
As of November 2026, the connection is not open yet, and Orange County expects it to be complete in early 2027. The county’s New Independence Parkway project page says construction activities run from September 2025 through early 2027. A May 2026 progress report put the $14.5 million project at more than 54 percent complete as of March 31, 2026, with completion expected in late January 2027.
Spectrum News 13 reported in March 2026 that work was underway and that the connection was expected to be complete in 2027. Dates can shift, so check the county project page for the latest schedule.
Where does the New Independence Parkway extension run and what does it connect?
The extension runs about one mile, from the current end of New Independence Parkway near CR 545, also called Avalon Road, west to the Lake and Orange county line, where it ties into Wellness Way. On the Orange County side it links Horizon West toward the SR 429 interchanges and the Hamlin area, while Wellness Way continues west toward Clermont.
Orange County describes the new road as a four-lane divided roadway, with two 11-foot lanes in each direction separated by a raised grass median and a 10-foot multi-use path on each side. For the parallel road work next door, see our Avalon Road widening page.
Who is building the Wellness Way connection?
Two counties are building it in separate segments. Orange County, through a public/private partnership, is delivering the one-mile New Independence Parkway extension from Avalon Road to the county line. Lake County is responsible for the Wellness Way segment on its side of the line.
Orange County is also advancing related corridor work in the same Horizon West package, including the Flemings Road extension to Sawgrass Bay Boulevard, on a similar early 2027 timeline. The earlier New Independence Parkway extension guide covers how this project first came together.
What is already built, under construction and planned?
Here is how the pieces break down as of November 2026. Built: New Independence Parkway already serves Horizon West up to its current end near Avalon Road. On the Lake County side, Wellness Way is Lake County’s road; we could not find a current official figure for how much of it is built. Under construction: the one-mile Orange County extension to the county line, which began in September 2025 and is expected to finish in early 2027.
Planned and related: continued Wellness Way development in south Lake County, which is a master-planned area of roughly 16,000 acres, along with other corridor projects such as the Flemings Road extension. The gap that remains today is the short stretch at the county line, and that is what the current construction is closing.
What does Jared Jones say about the Wellness Way connection?
In his July 2, 2026 video, Jared Jones predicts the connection will change what it feels like to live in Winter Garden and says the area is about to grow from a commercial standpoint once the road opens. He describes Wellness Way as a Lake County road already built about three miles in, with a gap left at the county line that Orange County is now closing so drivers can reach the SR 429 connector and the Hamlin area.
He estimated on camera that the road would be done within about six months of filming, which points to around early 2027 and lines up reasonably well with the county’s late January 2027 target. He also said there are roughly a thousand homes under construction on the Clermont side behind the connection, with two or three hundred already closed. His three-mile figure, the home count and the traffic and commercial-growth predictions are his own observations and estimates. We could not confirm the specific mileage or home numbers against a current official source, so treat them as Jared’s view rather than verified figures.
Why does the connection matter for traffic?
Orange County says the extension is meant to pull traffic off other east-west routes once it opens. The county’s Transportation Planning Division projects the completed road will move 7,000 to 9,000 vehicles per day off routes such as Schofield Road and Marsh Road.
Longer-range traffic models cited for the corridor project roughly 35,500 vehicles a day on the full extension by 2047, and about 43,000 on the western leg as Lake County grows. For how this fits the wider road network, see our Horizon West commute and roads guide.
Have questions about buying or selling here? Call or text 407-706-5000 or visit jaredjones.com.
Jared Jones Team, Brokered by eXp Realty.
Frequently asked questions
When will the Wellness Way connection to Horizon West open?
As of November 2026, it is not open yet. Orange County is extending New Independence Parkway about one mile to the Lake County line, where it meets Wellness Way. The county project page says construction runs from September 2025 through early 2027, and a spring 2026 progress report expected completion in late January 2027. Dates can shift, so check the county project page for the latest schedule.
Where does the New Independence Parkway extension run?
The extension runs about one mile from the current end of New Independence Parkway near CR 545, also called Avalon Road, west to the Lake and Orange county line, where it ties into Wellness Way. On the Orange County side it links Horizon West toward the SR 429 interchanges and the Hamlin area, while Wellness Way continues west toward Clermont on the Lake County side.
Who is building the Wellness Way connection?
Two counties are building it in separate segments. Orange County, through a public/private partnership, is delivering the one-mile New Independence Parkway extension from Avalon Road to the county line. Lake County is responsible for the Wellness Way segment on its side. Orange County is also advancing related corridor work, including the Flemings Road extension, on a similar early 2027 timeline.
What will the new road look like?
Orange County describes the New Independence Parkway extension as a four-lane divided roadway. It has two 11-foot lanes in each direction separated by a raised grass median, plus a 10-foot multi-use path on each side for walking and biking. The project is budgeted at $14.5 million and was reported more than 54 percent complete as of March 31, 2026.
How much traffic will the connection carry?
Orange County’s Transportation Planning Division projects the finished extension will move 7,000 to 9,000 vehicles per day off other east-west routes, including Schofield Road and Marsh Road. Longer-range traffic models for the corridor project roughly 35,500 vehicles a day on the full extension by 2047, and about 43,000 on the western leg as Lake County continues to grow.
What does Jared Jones say about the connection?
In his July 2, 2026 video, Jared Jones predicts the connection will reshape traffic and spark commercial growth once it opens. He describes Wellness Way as already built about three miles in on the Lake County side, with a gap at the line that Orange County is closing. He estimated completion within about six months of filming. The specific mileage and his home count are his own estimates, not verified figures.
Sources
- Orange County Government: New Independence Parkway project page (construction September 2025 through early 2027; data as of live page, checked Nov 18, 2026)
- Orange County Public Works: New Independence Parkway Extension Newsletter #1 (four-lane divided road, two 11-ft lanes each way, raised median, 10-ft path, connects to Wellness Way at the county line; data as of July 2025, checked Nov 18, 2026)
- Orange County Newsroom: transportation improvements in Horizon West (Horizon West road package including the Flemings Road extension on an early 2027 timeline; data as of Jan 2026, checked Nov 18, 2026)
- Spectrum News 13 (mynews13.com): work underway to extend New Independence Pkwy (construction underway; 7,000 to 9,000 vehicles per day projected off Schofield and Marsh roads; data as of Mar 11, 2026, checked Nov 18, 2026)
- The Orlando Real (Jim Carchidi): progress on 3 Horizon West road projects ($14.5 million project, more than 54% complete, completion expected late January 2027; data as of Mar 31, 2026 report, checked Nov 18, 2026)
- Welcome Wellness Way: project-area overview (Wellness Way described as a 16,000-acre master-planned area in southeastern Lake County; checked Nov 18, 2026)
- Jared Jones – Orlando Living (YouTube): Everything New and COMING SOON to Winter Garden 2026! (published Jul 2, 2026)
Related guides
- Winter Garden & Horizon West Real Estate (2026): Buy, Sell and Invest Hub
- New Independence Parkway Extension: What It Means for Clermont and Horizon West
- Is Avalon Road Being Widened in Horizon West? (2026)
- Which SR 429 Interchanges Serve Horizon West? (2026)
- When Will SR 516 Open? Lake/Orange Expressway Timeline (2026)
- What Is Being Built in Clermont and Minneola? Growth Projects and Census Data (2026)