Jared Jones Full Width Modern Header
Horizon West

Is Avalon Road Being Widened in Horizon West? (2026)

Written by Jared Jones
Updated November 2026
Winter Garden & Horizon West Real Estate Hub
Aerial view of new townhomes under construction beside graded land and a divided road along Avalon Road in Winter Garden, Florida
New homes going up along Avalon Road (CR 545) in Winter Garden. Orange County has been widening Avalon Road in phases; this photo shows nearby home construction, not a labeled widening segment.

As of November 2026, Orange County is designing a widening of Avalon Road (County Road 545) from two lanes to four along the roughly 1.6 miles between US 192 and Hartzog Road. Design is anticipated to finish in spring 2027. No construction start date is set.

2 to 4 lanesPlanned widening, US 192 to Hartzog Road
1.6 milesLength of the current segment
Spring 2027Design completion anticipated
C.R. 545County-maintained Avalon Road
At a glance (as of November 2026)
Fact Figure
Avalon Road designation County Road 545
Current widening segment US 192 to Hartzog Road
Segment length About 1.6 miles
Lane change Two lanes to four lanes
Planned travel lanes Four 12-foot lanes
Planned raised median 22-foot raised median
Design completion anticipated Spring 2027

Sources: Orange County CR 545 Avalon Road design page and its April 2026 draft study documents for the segment limits, length, lane plan and spring 2027 design target; the Orange County May 5, 2026 public hearing flyer for the schedule; the Orange County March 2024 RCA report (all checked November 16, 2026).

In this July 2, 2026 video, Jared Jones tours what is new and coming soon around Winter Garden and Horizon West. In the south Horizon West section he flags Avalon Road as still largely two lanes and a growing traffic pinch point. This page sets his on-the-ground take next to Orange County’s official widening plan and timeline.

Is Avalon Road being widened in Horizon West?

Yes. Orange County is designing a project to widen Avalon Road, which it identifies as County Road 545, from two lanes to four along the segment between US 192 and Hartzog Road. Avalon Road is a county-maintained road, not a state road or an expressway, so Orange County leads the work.

Per the draft study documents posted on the county’s CR 545 Avalon Road design page, the planned cross-section includes four 12-foot travel lanes, a 22-foot raised median, a 6-foot sidewalk on the east side and a 10-foot multi-use path on the west side, along with new signals, intersection upgrades, lighting and drainage. The county held a public hearing for the study on May 5, 2026.

Which part of Avalon Road is being widened and how long is it?

The current project covers about 1.6 miles between US 192 and Hartzog Road, the southern stretch closest to the US 192 corridor near Flamingo Crossings. The county’s draft study documents list US 192 as the only signalized intersection within the project limits.

The work grew out of a Roadway Conceptual Analysis the county finalized in March 2024 and is now in design. For how this stretch ties into the wider road network, see our Horizon West Commute and Roads Guide 2026.

When will the Avalon Road widening be built?

There is no construction start date yet. Orange County anticipates completing the design phase in spring 2027, and the May 5, 2026 public hearing flyer lists bid award, contract execution and construction phases as still to be determined.

The county also notes the schedule is subject to change due to funding or other potential delays, so treat any completion timing as unconfirmed. On the county’s schedule bar, right-of-way acquisition follows design, and the construction phases come after that.

What other Avalon Road improvements are planned?

The county’s March 2024 RCA report lists two more four-lane widenings in the area: Avalon Road from Hartzog Road to Water Spring Boulevard, and Avalon Road from Schofield Road to McKinney Road. Both are listed as planned improvements, and their current construction status is not confirmed.

Separately, a permanent traffic signal at the Schofield Road and Avalon Road intersection became operational in 2026, replacing a temporary signal. News coverage dated March 31, 2026 reported that the upgrade allows adjusted signal timing through the day for AM northbound and PM southbound peaks. For another nearby road timeline, see our SR 516 page.

What does Jared Jones say about Avalon Road traffic?

In his July 2, 2026 video, Jared Jones describes Avalon Road as still largely two lanes in the south and says the county is working on it. He calls traffic a caution in the fast-growing south Horizon West area.

He shares his own observations: afternoons can back up bumper to bumper toward the US 192 end, with what he describes as a mile of cars waiting through the same light on a two-lane road. He gives his opinion that the south Avalon Road corridor should have been four lanes sooner, and he adds that it will not be that way forever. These are his characterizations and opinions, not official traffic counts or county commitments.

What should buyers and commuters know about Avalon Road right now?

Treat the widening as planned and in design, not finished. As of November 2026 the county has a design target of spring 2027 for the US 192 to Hartzog Road segment, but no construction or opening date.

If a commute matters to you, drive the route at the times you would actually travel and confirm current conditions yourself, since project pages describe planned work rather than today’s lane count on every stretch. For broader context on area roads, see our Horizon West Commute and Roads Guide 2026 and our SR 516 timeline.

Have questions about buying or selling here? Call or text 407-706-5000 or visit jaredjones.com.

Jared Jones Team, Brokered by eXp Realty.

Frequently asked questions

Is Avalon Road being widened in Horizon West?

Yes. As of November 2026, Orange County is designing a project to widen Avalon Road, which it calls County Road 545, from two lanes to four between US 192 and Hartzog Road, a stretch of about 1.6 miles. Avalon Road is county maintained, so Orange County leads the work. The design phase is anticipated to be completed in spring 2027.

How long is the Avalon Road widening segment?

The current Avalon Road widening covers about 1.6 miles between US 192 and Hartzog Road, the southern stretch closest to US 192 near Flamingo Crossings. The county’s draft study documents list US 192 as the only signalized intersection within the project limits. The plan calls for four 12-foot travel lanes and a 22-foot raised median, replacing the existing two-lane road.

When will the Avalon Road widening be finished?

There is no construction or completion date yet. Orange County anticipates finishing the design phase in spring 2027, and its May 5, 2026 public hearing materials list bid award, contract execution and construction as still to be determined. The county also notes the schedule is subject to change due to funding or other potential delays, so any completion timing is unconfirmed as of November 2026.

Who maintains Avalon Road?

Orange County maintains Avalon Road, which it identifies as County Road 545. It is a county road rather than a state road or an expressway, so Orange County leads planning, design and construction of the widening. The current project runs from US 192 to Hartzog Road and is in the design phase as of November 2026, with design anticipated to finish in spring 2027.

Are other parts of Avalon Road set to be widened?

Orange County’s March 2024 planning report lists two additional four-lane widenings in the area: Avalon Road from Hartzog Road to Water Spring Boulevard, and Avalon Road from Schofield Road to McKinney Road. Both are listed as planned improvements, and their current construction status is not confirmed. Separately, a permanent traffic signal at Schofield Road and Avalon Road became operational in 2026.

What does Jared Jones say about Avalon Road?

In his July 2, 2026 video, Jared Jones describes Avalon Road as still largely two lanes in the south and says the county is working on it. He shares his own observation that afternoons can back up toward the US 192 end, and his opinion that the corridor should have been four lanes sooner. These are his characterizations, not official county figures or commitments.

Shopping Basket